Medical Centre – NSW

NSW – SEPTEMBER 2019
Industry Electrical Company Builder Zauner Constructions Project Duration 9 Months Scope of Project Supply & installation of
Industry | Electrical Company |
Builder | Zauner Constructions |
Project Duration | 9 Months |
Scope of Project |
Supply and installation of 720kva generator, 3,500 litre underground bulk fuel tank and associated fuel transfer system. |
Generator Supplied |
HSW-660 T5 Enclosed generator set |
Additional Services | Generator Power completed the installation of the underground fuel system including all excavation and back fill works. Design and installation of the fuel transfer system including controls |
GPA Involvement |
Generator was engaged to provide a turn key solution including all civil works for the underground bulk fuel tank and associated fuel transfer lines. A remote fuel fill point was installed for ease of bulk tank filling along with a fuel transfer system for transferring fuel from the bulk fuel tank to the generator day tank located at roof level. |